[FoxNews] USS Nimitz set for 2026 decommissioning while replacement Kennedy won't arrive until 2027, temporarily reducing fleet strength.
"Specifically, John F. Kennedy (CVN 79) construction was fairly advanced when many Ford lessons were realized, precluding timely implementation of lessons learned for Kennedy," Todd Corillo, HII company spokesperson, told the publication. "In contrast, Enterprise (CVN 80) and Doris Miller (CVN 81) have been able to incorporate, leverage and capitalize on Ford lessons learned earlier in the construction process."
"The CVN 80 delivery date shifted from September 2029 to July 2030 due to delays in material availability and industry/supply chain performance," the document’s footnotes read.
|